向阳变至沙田变110kV线路工程
监 理 规 划
湖南电力建设监理咨询有限责任公司 2012年 8月
批准:批准 批准: 年 年 年月 日月 日月 日
1
目 次
1 工程项目概况 ································································································································· 3
1.1 工程概况 ································································································································ 3 1.2 工程建设目标 ························································································································· 3
1.3 参建单位 ································································································································ 4 2 监理工作范围 ··············································································································· 4 3 监理工作内容 ··············································································································· 4 4 监理工作目标 ··············································································································· 8 5 监理工作依据 ··············································································································10 6 项目监理机构的组织形式 ·······························································································10 7 项目监理机构的人员配备计划 ·························································································10 8 项目监理机构的人员岗位职责 ························································································· 11 9 监理工作程序 ··············································································································14 10 监理工作方法及措施 ···································································································27 11 监理工作制度 ············································································································33 12 监理设施 ··················································································································34
2
1 工程项目概况 1.1 工程概况 1.1.1 工程名称
向阳变至沙田变110kV线路工程
1.1.2 工程地点
本线路工程起自向阳220kV变东侧110kV进出线龙门架,止于沙田变110kV进出线龙门架。位于宁乡县境内。 1.1.3 工程规模
线路路径总长25.246km,其中利用旧双回路线路长1.102km(N1~N6号与110kV向灰线共塔出线),新建单回路线路长23.724km,新建双回路0.42km(考虑到沙田变进线段通道受限制本次线路N94~N96号与待建的110kV黄沙线共塔进沙田变)。
本工程共有杆塔90基,其中有自立式铁塔46基,电杆26基,拉门塔18基。
本工程导线向阳变出线段(向阳变龙门架~N6)1.102km导线(JL/G1A-240/30型钢芯铝绞线)利旧,N6~沙田变新建段24.144km导线采用JL/G1A-240/40型钢芯铝绞线。向阳变出线段(向阳变龙门架~N6)1.102km架空地线(XGJ-50型稀土锌铝合金镀层钢绞线)利旧同时新架设ADSS光缆;与利旧线路相邻耐张段(N6~N9)0.694km架空地线采用GJ-50镀锌钢绞线及架设ADSS光缆;N9~N17和N81~N94两段线路5.56km架空地线一根采用OPGW-13-90-1型24芯光钎复合地线、另一根采用JLB20A-80-7铝包钢绞线分流地线;其余新建线路段(N17~N81)17.47km架空地线一根采用OPGW-13-90-1型24芯光钎复合地线、另一根采用GJ-80型镀锌钢绞线。
绝缘子型式均采用U70BP/146-1的标准型钢化玻璃绝缘子。
1.1.4 工程地形地貌、地质、交叉跨越及特点
地形地貌:丘陵约占44%、山地约占49%、水田约占7%。线路途径主要为水田、丘陵、山地交错分布,高程介于50~400m,局部相对高差较大。植被以松、杂树及竹为主,水土保持较好,丘陵、山地上部为黄色可塑、硬粘性土,系残坡基层,下部为基岩,部分山地为岩石。
基础地质:泥水7%、坚土35.5%,松砂石41.9%,岩石15.6%。
交叉跨越:跨待建高速1处;跨省道2处;跨乡村公路7处;跨河流2处;跨35kV电力线3处;跨10kV电力线13处;跨380V及以下电力线75处;跨通讯线66处;跨房屋9处;铁路1处。
工程特点:
(1) 杆塔采用典型设计和高跨原则,减少了树木砍伐量。 (2) 电杆采用明导通,有效地提高了防雷效果。
(3) 建设管理单位要求本工程达标投产并创网优工程,工程质量、安全、资料及其它各项管理工作要求高,各参建单位要周密策划并认真实施。
(4) 本工程地处平江山区,部分地段杆塔位地形较陡,施工中要注意着重防患基础保护边距不够和接地沟顺山坡开挖的质量通病。在杆塔组立中施工项目部要加强对危险地形施工的安全监控
(5) 线路沿线的民风较纯朴,地方协调工作难度相对较小,但由于地形及土质等原因,加上施工工期较紧,故施工难度较大。
1.1.5 计划投资及工期要求
本工程施工图设计概算××××万元。
工程计划工期:2010年9月10日开工,2011年1月22日具备送电条件。 1.2 工程建设目标 (1.2条的内容以《建设管理纲要》中的要求为准) 1.2.1安全控制目标
(1)不发生人身轻伤及以上事故;
3
(2)不发生因工程建设引起人员责任的电网、设备一类障碍; (3)不发生一般施工机械设备损坏事故; (4)不发生一般火灾事故。 (5)不发生一般环境污染事件。
(6)不发生负同责任及以上的一般交通事故; (7)不发生对公司造成影响的安全事件。
1.2.2 质量控制目标
(1)、工程“零”缺陷移交,质量总评为优良,并满足分项工程合格率100%,单位工程优良率100%。 (2)、实现工程达标投产及创国家电网公司优质工程目标(达到规模的500kV新建输变电工程争创国家优质工程)。
(3)、“标准工艺”应用率≥80%。
(4)、不发生下列及以上质量事件:1) 设备在安装、调试期间,由于保管、操作不当,造成设备严重损坏需返厂进行返修处理,但不影响设备的正常使用和工程寿命;2) 由于工艺差错、构件规格和加工问题,造成批量返工。 1.2.3 进度控制目标
(1)确保工程2010年9月10日开工。
(2)确保工程里程碑各节点计划的实现。
基础施工:2010年9月10日-2010年10月20日。 杆塔组立:2010年10月15日-2010年11月25日。 架线施工:2010年11月20日-2010年12月25日。 竣工验收:2011年1月10日-2011年1月12日。 竣工验收消缺复查:2011年1月13日-2011年1月17日。 受电时间:2011年1月18日-2011年1月22日。 (3)确保工程2011年1月22日竣工送电。 1.2.4 造价控制目标
(1)严格管理施工承包合同规定范围内的承包总费用,监理范围内的工程,工程总投资控制在批准的概算范围之内。
(2)按照合同规定的程序和原则履行好投资控制职责,积极配合设计、施工单位进行技术优化工作,并及时主动反映、协调有可能对工程投资造成影响的任何事宜。 1.3 参建单位
项目法人:湖南省电力公司
建设管理单位:湖南省电力公司岳阳电业局 设计单位:湖南岳阳电力勘测设计院
监理单位:湖南电力建设监理咨询有限责任公司 施工单位:湖南岳阳湘岳电力有限公司 运行单位:岳阳电业局平江电力公司 质监单位:岳阳电力建设工程质量监督分站
2 监理工作范围
本工程监理的服务范围是对汉昌-长寿110kV输电线路工程进行四控制(安全、质量、进度、投资)、二管理(信息、合同)、一协调(相关单位的工作关系),监理工作从施工准备开始至竣工投产一年后的
4