2工程量的计算
2.1基础工程 2.1.1平整场地
S= (12.3+0.245×2) ×(30+0.245×2) =389.97(m2) 2.1.2 挖地槽
L外=(12.3+0.0625×2)×2+(30+0.0625×2)×2=85.1(m) S外=(1.05+0.3×2+0.37×1.55)×1.55=3.446425(m2) L内=[30-(0.46+0.3)×2]×2+[5.1-(0.46+0.3)-(0.52+0.3)]×12+[2.1-(0.52+0.3)×2]×3=100.58(m) S内=(1.04+0.3×2+0.37×1.55)×1.55=3.430925(m2) ∴ V=L外?S外+L内?S内
=85.1×3.446425+100.58×3.430925 =638.37(m3) 2.1.3基础回填土
2.1.3.1室外地坪以下砖体积 L外=85.1m
S外=0.365×(1.387+0.216)+0.063×(0.0625×8+0.365)=0.64(m2) L内=(5.1-0.24)×12+(30-0.12×2)×2+(2.1-0.24)×3=123.42(m) S内=0.24×(1.45+0.788)=0.537(m2)
∴ V室外以下砖=85.1×0.64+0.537×123.42=120.76(m3) 2.1.3.1 C10混凝土垫层 L外85.1m
L内=100.58+0.3×2×17=110.78(m)
∴ V垫层=85.1×(1.05×0.1)110.78×1.04×0.1=20.46(m3) 2.1.3.3 基础回填土
V=638.37-120.76-20.46=497.15(m3)
2.1.3.4房心回填土
S主墙土=(12.3-0.24)×(30-0.24)-0.24×123.42=329.2848(m2) h回填=0.3-0.24=0.06(m)
∴ V房心回填=329.2848×0.06=19.76(m3) 2.1.3.5余土外运
V=638.37-497.15-19.76=121.46(m3)
2.2混凝土工程
2.2.1 基础部分 2.2.1.1 地圈梁 L外=85.1m L内=123.42-1.86×3-3.36-5.36=109.12(m)
∴ V=0.365×0.24×85.1+0.24×0.24×109.12-0.24×0.24×0.24×
26=13.38(m3)
2.2.1.2 构造柱 V
?0.30以下=(0.24×0.33×17+0.24×0.3×4+0.24×0.36×5)×0.5=1.0332(m3)
V?0.30以上=(0.24×0.33×18+0.24×0.3×8)0.3=0.60048(m3) ∴ VGZ=1.0332+0.60048=1.63(m3) 2.2.2 一层结构 2.2.2.1 构造柱
V外墙=(0.24×0.33×13+0.24×0.3×4)×3.55=4.68(m3) V内墙=(0.24×0.33×5+0.24×0.3×4)×3.55=2.43(m3) ∴ VGZ=7.11(m3) 2.2.2.2 过梁
2.2.2.2.1 外墙预制过梁:
VC1=2.28×0.365×0.12×14=1.40(m3) VC4=1.68×0.365×0.12×2=0.15(m3) ∴ VYZ=1.55m3 2.2.2.2.2 外墙现浇过梁:
VM2=[(2.1+0.24)×0.365×0.3-0.24×0.24×0.3×2]×2=0.44(m3) VM3=2.2×0.365×0.3=0.24(m3) ∴ VXJ=0.68m3 2.2.2.2.3 内墙预制过梁:
240 墙:VM4=1.48×0.24×0.12×15=0.63936(m3) VM5=1.28×0.24×0.12=0.036864(m3) VC5=1.98×0.24×0.12=0.057024(m3)
120 墙:VM5=1.28×0.12×0.12=0.018432(m3) ∴ VYZ=0.75 m3 2.2.2.2.4 内墙现浇过梁:
240 墙:VM5=1.17×0.24×0.12=0.033696(m3) 120 墙:VC6=1.1×0.2×0.35=0.077(m3) ∴ VXJ=0.11 m3
∴ 一层过梁:VXJGL=0.11+0.68=0.79(m3) VYZGL=1.55+0.75=2.3(m3) 2.2.2.3 圈梁 2.2.2.3.1 外墙
L外=85.1-(5.6+0.6-0.12×2)79.14(m)
V外=79.14×0.24×0.24-0.24×0.24×0.24×15=4.35(m3) 2.2.2.3.2 内墙
V内=(5.1-0.24)×12+(30-0.24)×2-3.36-5.36=109.12(m)
V内=109.12×0.24×0.240.24×0.24×0.24×9=6.160896(m3)
∴ VQL=10.5 m3 2.2.2.4 单梁,连续梁
LL1: V1=0.24×(0.3-0.11)×4×1.96+0.18×0.24×
LL LL LL LL LL∴ V2.2.2.5 2.2.2.6 V V V∴ V2.2.2.70.06×2=0.36(m3)
2: V2=[0.25×(0.5-0.11)×4.86+0.18×0.25×0.26×2]×4+
8×0.24×0.18×0.49=2.16(m3)
3: V3=0.25×(0.5-0.11)×4.86=0.47385(m3) 4: V4= (5.6+0.6-0.24)×0.365×0.55-0.24×0.24×0.55×2
=1.13(m3)
5: V5=0.25×(0.55-0.11)×5.36=0.5896(m3)
6: V6=0.2×(0.3-0.1)×(2.5-0.18) +0.15×0.18×0.2=0.1(m3) LL=4.92 m3 板
110mm 厚板:
V1=[(30-0.24)×(12.3-0.24)-3.36×5.105-3.06×4.86-
0.24×109.12]×0.11=33.08(m3) 100mm 厚板:
V32=3.06×4.86×0.1=1.48716(m)
雨篷
a?a=1.1×0.12×(5.6+0.6-0.22×2)=0.76032(m3) b?b=0.72×0.1×(2.1+0.24-0.15)×2=0.31392(m3) c?c=0.92×0.1×(2.2-0.16)=0.18768(m3) YP=1.26 m3 栏板
Va?a=+0.6×0.1×(5.76+0.1+1.15×2)+0.06×0.18×(1.23×2+6.02)
+0.06×0.1×(6.14+1.29×2)=0.643968(m3)
Vb?b=0.08×0.25×(0.76×2+2.26)×2=0.1512(m3) Vc?c=0.08×0.25×(0.96×2+2.12)=0.0808(m3) ∴ VLB=0.88 m3 2.2.2.8 楼梯
S= (5.1-0.12+0.125)×(3.6-0.24)17.1528(m3)
2.2.3 二层结构 2.2.3.1 过梁
2.2.3.1.1 外墙预制过梁
Vc?1=2.28×0.365×0.12×15=1.498(m3) Vc?4=(1.2+0.48)×0.365×0.12×2=0.147(m3) ∴ VYZ=1.64 m3 2.2.3.1.2 外墙现浇过梁:
Vc?30.365×0.12×(1.5+0.36)×2=0.1629(m3) ∴ VXJ=0.16 m3 2.2.3.1.3 内墙预制过梁: 240 墙
VM?4=1.48×0.24×0.12×11=0.468864(m3) VM?5=1.28×0.24×0.12=0.036864(m3) ∴ VYZ=0.505728 m3 120 墙
VM?6=1.28×0.115×0.12=0.017664(m3) 2.2.3.1.4 内墙现浇过梁
240 墙 VM?5=(0.8+0.12+0.25)×0.24×0.12=0.034(m3) VM?6= (1.5+0.36)×0.24×0.12=0.053568(m3)
∴ VXJ=0.087 m3