Systems Engineering Experiment Ⅳ
1. Experiment Objectives:
Recall project management operation and have a quiz in class
2. Experiment Tasks:
Task 1: Solve the following problem:
Construct the project network for a project with the following activities list. Please calculate
the engineering time, and find the critical path.
Series Numbers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Activity A B C D E F G H I J K L M N Immediate Predecessors - A B B B C D, E F G, H I I J K L Estimated Duration 1 Month 2 Months 4 Months 3 Months 2 Months 3 Months 5 Months 1 Month 4 Months 2 Months 3 Months 3 Months 5 Months 4 Months
Task 2: A quiz
Open file of ORtest2.htm and give the answer to each problem, submit the answer and get the score.
11
百度搜索“77cn”或“免费范文网”即可找到本站免费阅读全部范文。收藏本站方便下次阅读,免费范文网,提供经典小说综合文库系统工程实验课指导书(3)在线全文阅读。
相关推荐: