P1103高压煤浆泵检修方案
P1103( )高压煤浆泵检修方案
编制:
审核:
审定:
批准:
P1103高压煤浆泵检修方案
目录
一. 检修原因及目的 ··································································· 3 二. 检修组织机构 ······································································ 3 三. 检修前准备工作 ··································································· 4 四. 主要检修内容及程序 ····························································· 4 1. 拆解进出口单向阀: ····························································· 4 2. 拆一次,二次软管。 ····························································· 5 3. 拆下单向阀后,短管检查内部有无渣块,用气体吹通管线。 ·········· 5 4. 补油盘的检查及清理。 ·························································· 6 5. 出口缓冲管的检修: ····························································· 7 6. 拆卸蓄能器 ········································································· 7 7. 气囊中氮气的加注量及方法: ················································· 9 8. 推进液的加注及泵单体试车: ················································· 9 五. 质量验收 ·········································································· 10 六. 注意事项 ·········································································· 10 七. 环保要求 ··········································································· 11 八. 九.
2
质量控制和验收程序 ························································· 11 网络进度及劳动力需求计划 ··············································· 12
P1103高压煤浆泵检修方案
一. 检修原因及目的
检修原因:例行常规周期检查修复,消除隐患。
检修目的:根据运行周期、煤浆泵备件使用状况对煤浆泵的进出口单向阀进行检查、入口管线进行清洗疏通、出口缓冲罐单向阀检查测量、调整油分配盘推杆热膨胀间隙、对油路进行疏通。
二. 检修组织机构
检修由气化、电气、计控车间和维修中心共同配合完成,为保证各检修项目按期、保质、保量的完成,特成立煤浆泵检修领导组织机构,以组织协调各方检修力量,达到文明、安全、高效、节约的检修目的。 组 长: 副 组 长:
成 员: 、 、 、 、 人员分工:
组长: 全面负责本次检修的组织与协调工作,负责材料备件的落实,检修方案编制、审核,落实检修前的工艺处理、施工人员的安全教育、各检修项目的验收,检修人员的协调。
副组长:协助组长完成各自具体分管的检修工作,组织协调好相应车间的检修力量,完成好各自的检修项目。
成员:协调各部门完成具体的检修工作,工器具的准备。根据检修要求完成检修任务,填写检修顺序确认表。
3
P1103高压煤浆泵检修方案
三. 检修前准备工作
检修前详细统计设备缺陷,有针对性检修。提前落实检修备件(具体见检修材料表)及所需工器具,做好动员工作,要求全部人员必须全部全程的不分工种的参加检修,对检修进行技术交底、危险辨识、作业安全事项交底和落实检修人员责任分工。检修项目以及注意事项详细阅读检修任务指导书,如有疑问,向检修片区技术人员请教,保证检修顺利进行。
四. 主要检修内容及程序
1. 检修前工艺处理:
与工艺车间协调,检修前准备干净的68#抗磨液压油桶两个,要求工艺小夜班排净液压端液压油,油品放置指定地点,用塑料布包好,联系分析取样分析(机械杂质、水分)。
2. 拆解进出口单向阀:
a.用65mm扳手(液压扳手力矩调节为Ma=2560Nm),松动进出口单向阀紧固螺栓,取出压紧杆。旋出阀体。保存单项阀密封垫。
b.首先取下导向套,用铜锤向下敲击单向阀导杆,取出单向阀,清理阀体中积渣。检查单向阀密封垫是否有严重的缺边和变型。用手压缩弹簧,检查弹簧的压缩能力,是否有裂纹。
c.清理后回装单向阀,在阀体中灌水,从阀体下部观察,如果水成串滴漏,就需要更换阀芯及阀座(必须是成对更换)。同时检查表面喷涂层是否有脱
4
P1103高压煤浆泵检修方案
落或严重磨损,以便分析其运行情况。
3. 拆一次,二次软管。
a.扳手松开一次软管上部压盖大法兰四条紧固螺栓。安装吊环,移出大法兰盖。下端同法移开法兰。上下两人配合取出软管,标明软管的方向及所在缸体位号。
b.检查工艺排净推进液,使用17mm内六角扳手松开薄法兰四条内六角紧固螺栓。取下端固定法兰,上下两人配合,取出软管。 c.清理:
①.清理法兰密封面,疏通压力开关检测点,检查油路管线是否通畅,清理排液环系。
②.取出缸体上部密封圈,取密封圈前标明方向,圆滑过渡部位向内与软管接触,直角倒边向外,下部与缸体之间留有通道,方便排净油中气体。取出密封环后,用煤油清理密封口,然后用干净的抹布,擦拭干净。 ③.取下缸体上部,南侧油路排气单向阀,用气吹通缸体侧管路。拆解单向阀并清理单向阀,清理回装后用嘴逆气体流动方向吹,检查单向是否好用,起到止逆作用。阀门开启压力为0.8bar=0.8MPa。
4. 拆下单向阀后,短管检查内部有无渣块,用气体吹通管线。
(1) 回装一次二次软管,加注防冻液。
a.两人配合安装软管,要求软管箭头向上,厂家标识向外。用手压平软管边缘,然后安装上下固定法兰,然后安装一次软管,用手压平软管压边后
5